Reschedule Isolation Orders and Permits
Explanation
Use this activity to reschedule Isolation Orders and 
Permits (and work orders). 
Prerequisites
	- Isolation orders and permits must exist in the 
	system.
 
	- To reschedule a work order the permit should be 
	connected to the work order.
 
	- The status of the isolation order and/or permit 
	should be Preparation Approved or below.
 
System Effects
The selected isolation order, permit and/or work order 
will be rescheduled. 
Window
Isolation and Permit Planning
Related Window Descriptions
Isolation Permit Planning
Change Date 
Change Dates for Isolation 
Order
Procedure
	- Open the 
	Isolation and Permit Planning 
	window and query for the relevant record (F3).
 
	- To move the node, select the horizontal bar, 
	drag and drop it at the required time slot. 
 
	- To change the duration of
	the node, resize the 
	bar or double-click on the bar and enter new start and end dates and times 
	in the dialog box that appears.  
 
	- Click OK. 
	Note: The dialog box that appears 
	will differ based on the type of the node you have selected, for isolation orders it is
	Change Dates for Isolation Order, for permits and work orders 
	it is Change Date.