Approve Permit
Explanation
This activity is used to approve a permit. An 
approved permit does not usually require a revision, however if such a 
requirement does arise you can revise it by changing the status to UnderPreparation 
(right-click, point to Permit Status and click Revise). 
When the revision has been made you can once again approve the permit.
In addition, a permit with the PreparationApproved 
status can also be 
cancelled if required, provided no isolation orders are connected to it.
Prerequisites
A permit must have been defined and isolation orders 
connected (if required) in the 
Permit window.
System Effects
As a result of this activity the permit is approved, 
and will receive the PreparationApproved status. 
Window
Permits
Permit
Related Window Descriptions
Permits
Permit
Permit/Prepare
Procedure
	- Open the 
	 Permit window and query for 
	the permit that should be approved (F3).
 
	- Click the 
	Prepare tab.
 
	- Enter the signature of the person who prepared the permit in the 
	Prepared By field. Use the List of Values to select a suitable value. 
	Note: If this field is left empty, the ID of the logged-on user is 
	retrieved automatically to this field when the status of the permit is set 
	to Prepared.
 
	- Enter the signature of the work leader in the Work Leader field. Use the 
	List of Values to select a suitable value.
 
	- Save the information (F12).
 
	- Right-click on the window, 
	point to Permit Status and click Prepare.
	
 
	- Next enter a 
	value in the Approved By field. Use the List of Values to select a 
	suitable value. Note: If this field is left empty, the ID of the 
	logged-on user is retrieved automatically to this field when the status of 
	the permit is set to PreparationApproved.
 
	- Save the information (F12).
 
	- Right-click, point to Permit Status and click Approve Preparation.