Define Actual Markups
Explanation
This activity is used to enter actual markups which are markup values 
assigned to project  
cost/revenue elements. In this activity actual markups will be 
defined for a company and any new sales contracts created will 
automatically inherit these markups. 
Prerequisites
Project 
cost/revenue elements should be predefined for the company in the 
Project Cost/Revenue Elements window. 
System Effects
The predefined markups based on project cost elements will be used as a basis 
for defining which markups are available for a given sales contract. 
Window
Sales Contract Basic Data
Related Window Descriptions
Sales Contract Basic Data/Markups/Actual Markups
Procedure
	- Open the Sales Contract Basic Data window, click the 
	Markups tab and then click the 
	Actual Markups 
	tab.
 
	- Click in the Company ID field and query for the company that you 
	want to define the markup on. 
 
	- Create a new record in the lower part of the window. 
 
	- In the Project Cost Elements field, use the List of Values to 
	select a project cost element for 
	which you want to define the markup.
 
	- In the Markup field, enter a markup value to fit the project 
	cost 
	element. 
 
	- Click Save.