Set Contract Change Order to Analysis in Progress
Explanation
Use this activity to set an accepted contract change order to the
Analysis in Progress status. When you set the status to Analysis in Progress, 
it means that the analysis of the change requirements should 
continue in the change process and be further investigated e.g. concerning the 
impact of the change. 
Prerequisites
	- A contract change order in the Preliminary status should exist.  
 
System Effects
	- A Contract Change Order is set to the Analysis in Progress 
	status.
 
	- A history record with the status change is created 
	and displayed in the Contract Change Order/History tab.
 
Window
Contract Change Order
Related Window Descriptions
Contract Change Order
Procedure
	- Open the Contract Change Order 
	window 
	and query for contract change orders in the Preliminary status.
 
	- Select a contract change order that should be accepted. Right click and 
	click Status, and then select the Start Analysis menu option.
 
	- Click Yes to continue to set the contract change order to the Analysis in Progress 
	status.