Set Contract Change Order to Active
Explanation
This activity is used to set the contract 
change order 
to the Active status. When the status has been set to Active, it indicates 
that the change described in the contract change order is ready to be executed 
e.g. by activating a new revision in a contract or by adding a new activity to a 
project plan. It is possible to activate a sub/sales contract 
	revision, if a contract change order has been entered on a contract line 
	item.
Prerequisites
	- A contract change order should exist in the  
	Approved status.
 
	- Any approval lines and approval routing steps for 
	the status change, should be approved.
 
System Effects
	- The status of the contract change order is changed to Active.
 
	- A history record with the status change is created 
	and displayed in the Contract Change 
	Order/History tab.
 
Window
Contract Change Order
Related Window Descriptions
Contract Change Order
Procedure
	- Open the Contract Change 
	Order window and query for the contract change orders which should be 
	activated.
 
	- Right click on the header and click Status, then select the Set Active 
	menu option.
 
	- Click Yes to continue to set the contract change order to Active.